Hillmorton Junction Lighting

Hillmorton

Client: Birse Rail
Type of Project: Junction Lighting
Value: £55k

The West Coast Main Line (WCML). The purpose of the lighting was to provide an appropriate level of illumination that would permit maintenance activities currently undertaken in daylight to be done during the night, when access is more readily available. “Flat Beam” Technology lights were used, set at 1.5m above rail level on posts and high level on existing structures.

Works comprised of:

  • Installation of light fittings onto the pre-installed columns
  • Installation of connection boxes onto the base of the columns
  • Installation of lighting control equipment
  • Electrical supply alterations
  • Installation of cables into the existing troughing routes/ UTX
  • Testing & Commissioning