High Wycombe, Princess Risbourgh and Beaconsfield
Client: MPB Structures.
Service: Lighting Column, PA and SPT Installation.
Overview
The UP platform at High Wycombe Station, Platforms 2 and 3 at Princes Risbourgh and platforms 1 and 2 at Beaconsfield were to be extended as part of the Chiltern Mainline Platform Extension Project. New lighting columns, PA equipment and SPT’s were to be installed at all three stations.
Our works consisted of;
- Lighting column installation/PA
- SPT Installations
- Equipment Installation (test & commissioning covered within TEW plus WPP)
- Electrical Works/Testing
- Cable Installation (DOO) – new platform only
- Electrical Works
- Cable installation