Finsbury Park to Alexandra Palace

Client: Balfour Beatty Rail
Type of Project: Station Platform, Lighting & Power
Value: £470k

To improve performance and capacity on the ECML, the scope of the scheme was to allow Hertford/Gordon Hill to Moorgate and vice versa inner suburban services to operate independently of other inner suburban, outer suburban and LDHS services in both directions between Finsbury Park and Alexandra Palace.

RES were tasked with the Design and installation of Station Lighting, Small Power, Distribution Equipment and Cable Management for the above while also supporting Comms and DOO installations.

Works consisted of;
  • Intrusive survey, Form B specification, drawings, calculations, assessments.
  • Contract Responsible Engineer Duties.
  • Reconfiguration of existing & new DOO equipment.
  • New water supply & mechanical fit out to station buildings.
  • OLE traction bonding.
  • New fire alarm & security system.
  • Lift motor rooms fit out small power, lighting ventilation & heating.
  • Lift power supplies.
  • Platform, canopy, subway & station buildings lighting.
  • Installation of mains, sub mains cabling & CMS.
  • Reconfiguration of existing sub mains & cabling.
  • New mains, sub mains switchgear & lighting control.